Story Point Estimation Guide

CMS Planner uses Fibonacci sequence-based story point estimation to account for increasing uncertainty with larger tasks. This guide explains the framework and how to apply it effectively.

Fibonacci Sequence

Story points follow the Fibonacci sequence: 1, 2, 3, 5, 8, 13, 21, 34+

Why Fibonacci?

  • Uncertainty increases non-linearly - Larger tasks have more unknowns
  • Prevents false precision - Gap between numbers acknowledges uncertainty
  • Forces decomposition - Very large numbers indicate tasks need breaking down
  • Industry standard - Widely used in Agile/Scrum methodologies

Story Point Scale

Points Time Estimate Complexity Examples
1 <2 hours Trivial Update footer text, change button color, fix typo
2 2-4 hours Simple Add form validation, create basic component, simple bug fix
3 4-8 hours (1 day) Standard Implement search filter, CRUD API endpoint, standard feature with tests
5 2-3 days Complex Auth flow, payment gateway, multi-component feature
8 3-5 days Major Real-time notifications, complex dashboard, architecture decisions
13 1-2 weeks Epic User management system, e-commerce checkout, should be broken down
21 2-3 weeks Large Epic Complete theme, full content model, must be broken down
34+ >3 weeks Too Large Must be decomposed into smaller epics before planning

What Story Points Measure

Story points measure complexity and effort, not just time:

Factors Considered

  1. Complexity - How difficult is the work?
  2. Uncertainty - How well understood is the requirement?
  3. Effort - How much work is involved?
  4. Dependencies - What else must be complete first?
  5. Risk - What could go wrong?

NOT Time Estimates

While we provide time ranges for reference, story points are relative measures of effort.

  • 5 points for Developer A might take 2 days
  • 5 points for Developer B might take 3 days
  • Both are still 5 points of complexity

Estimation Best Practices

Include Everything

Story points should include time for:

  • Implementation - Writing the code
  • Testing - Unit, integration, manual testing
  • Code review - Review cycle and revisions
  • Documentation - Code comments, README updates
  • Deployment - Configuration, deployment steps
  • Bug fixes - Addressing issues found in testing

Consider Complexity Factors

  • Technical complexity - Algorithm difficulty, architecture decisions
  • Integration complexity - Number of systems/components to integrate
  • Unknown requirements - Ambiguity or research needed
  • Team experience - Familiarity with technology
  • Dependencies - Blocking or parallel work

Add Uncertainty Buffer

  • Higher points = more buffer - 21 points has more uncertainty than 3 points
  • Unknown tech = higher points - New framework? Add buffer
  • Vague requirements = higher points - Unclear acceptance criteria? Add buffer
  • External dependencies = higher points - Waiting on third parties? Add buffer

Recipe-Based Projects

For Drupal recipes and similar architectures, estimate separately:

  1. Recipe creation (8-13 points)
  2. Define configuration entities
  3. Export configuration
  4. Organize structure
  5. Test clean installation

  6. Configuration export (2-3 points per entity)

  7. Content type configuration
  8. View configuration
  9. Field configuration

  10. Testing (3-5 points per recipe)

  11. Clean installation test
  12. Dependency testing
  13. Field storage verification

  14. Documentation (2-3 points per recipe)

  15. README file
  16. Installation instructions
  17. Dependency documentation

  18. Demo content (5-8 points per recipe)

  19. Create sample content
  20. Export with Default Content
  21. Verify import works

WordPress Block Theme Projects

For WordPress 6.8+ block themes with Full Site Editing, estimation depends heavily on the block vs pattern vs ACF vs custom block decision. This choice can impact development time by 3-10x.

Story Points to Hours Conversion

While story points are relative measures, stakeholders often need hour estimates for budgeting. Use these conversion guidelines for WordPress projects:

Story Points Time Estimate Typical Use Cases
1 point 2 hours Simple pattern with 3-5 core blocks, basic config changes
2 points 4 hours Small pattern (6-10 blocks), simple ACF block, plugin setup
3 points 6-8 hours (1 day) Complex pattern, theme.json setup, basic ACF block with logic
5 points 12-16 hours (2 days) Multi-section patterns, complete theme.json, ACF block with repeaters
8 points 24-32 hours (3-4 days) Major features, custom static Gutenberg block, performance optimization
13 points 40-80 hours (1-2 weeks) Epics, dynamic Gutenberg block with REST API, complex integrations
21 points 80-120 hours (2-3 weeks) Large epics, complex block libraries, advanced features
34+ points Must decompose Break into smaller epics (13 points or less per epic)

Important: These are estimates for planning, not guarantees. Actual time varies by developer experience, complexity, and unknowns.

Block Theme Foundation (5-8 points, 20-32 hours)

theme.json v3 Configuration: - Basic (colors, typography, spacing): 3 points (6-8 hours) - 6-8 colors - 2 font families, 5-7 font sizes - 8-10 spacing presets - Basic layout settings

  • Complete (+ element styles, custom settings): 5 points (12-16 hours)
  • Everything in Basic
  • Element styles (links, headings, buttons)
  • Border radius, shadows, gradients
  • Block-specific style overrides

  • Advanced (+ style variations, complex presets): 8 points (24-32 hours)

  • Everything in Complete
  • Multiple style variations (light/dark themes)
  • Complex block-specific settings
  • Custom template configurations

Basic Templates: - index, single, page, 404 templates: 2-3 points (8-12 hours) - Header/footer template parts: 1-2 points (4-8 hours)

Block Pattern Creation (1-5 points per pattern)

Patterns are reusable combinations of core blocks - the most efficient approach for most layouts.

Pattern Complexity Story Points Time Typical Examples
Simple (3-5 blocks) 1-2 points 2-4 hours Hero with Cover + Heading + Button; CTA with Group + Paragraph + Button
Moderate (6-10 blocks) 2-3 points 4-8 hours Feature grid with Columns + Images + Headings + Paragraphs; Multi-section landing page
Complex (10+ blocks) 3-5 points 8-20 hours (1-2 days) Full page layouts; Nested groups with advanced styling; Multi-level navigation

Estimation Factors: - Number of blocks (each block = ~15-30 minutes) - Nesting depth (nested groups add complexity) - Custom styling (beyond theme.json) - Responsive behavior (mobile/tablet/desktop variations)

ACF Block Development (2-5 points)

ACF blocks use PHP templates + custom fields - faster than custom Gutenberg blocks for field-heavy components.

ACF Block Complexity Story Points Time Typical Examples
Simple (basic fields, PHP template) 2-3 points 4-8 hours Team member (name, title, bio, photo); Location card (address, phone, hours)
Complex (repeaters, conditional logic, relationships) 3-5 points 12-20 hours (1-2 days) Service listing with repeating features; Product showcase with conditional pricing

Requirements: - ACF PRO license ($49-249/year) - PHP templating knowledge - Field configuration time

Estimation Factors: - Number of fields (each field = ~15-30 minutes) - Repeater fields (add 1-2 hours per repeater) - Conditional logic (add 1-2 hours per condition set) - Relationship/post object fields (add 2-4 hours)

Custom Gutenberg Block Development (3-21 points)

Custom blocks are React-based - reserve for truly interactive features. Most expensive option.

Block Type Story Points Time When to Use
Simple Static Block 3-5 points 12-20 hours (1-2 days) No backend logic, basic UI, could consider ACF instead
Block with InnerBlocks 8-13 points 32-80 hours (3-5 days to 1-2 weeks) Container blocks, nested content patterns, strict block validation
Dynamic Block with REST API 13-21 points 80-120 hours (1-3 weeks) Interactive UI with state management, REST API integration, complex data fetching

Requirements: - React knowledge - WordPress block editor API - Build tooling (@wordpress/scripts, webpack, npm) - Testing (Jest, React Testing Library)

Estimation Factors: - Block attributes (each attribute = ~30-60 minutes) - InspectorControls (sidebar settings = +2-4 hours) - InnerBlocks configuration (each level = +4-8 hours) - Backend PHP rendering (add 2-4 hours) - REST API endpoints (each endpoint = +4-8 hours) - State management complexity (add 4-8 hours)

Performance Optimization (5-13 points)

Core Web Vitals are mandatory for WordPress projects (Google Search ranking factor since 2021).

Optimization Level Story Points Time What's Included
Initial Setup 5-8 points 20-32 hours (3-4 days) Caching plugin, image optimization, lazy loading, critical CSS, font optimization, Core Web Vitals baseline
Ongoing Monitoring 2 points/sprint 4-8 hours Lighthouse audits, Core Web Vitals tracking, performance gate enforcement, issue remediation

Core Web Vitals Targets: - LCP (Largest Contentful Paint): < 2.5 seconds - INP (Interaction to Next Paint): < 200ms - CLS (Cumulative Layout Shift): < 0.1

Estimation Factors: - Current performance baseline - Asset size (JS/CSS/images) - Number of plugins - Hosting quality

Plugin Setup and Configuration

Plugin Complexity Story Points Time Examples
Simple (install, activate, basic config) 1 point 2 hours WP Rocket, Yoast SEO, Wordfence, Imagify
Complex (extensive config, testing, integration) 2-3 points 4-8 hours Gravity Forms with conditional logic, ACF PRO with custom field groups
E-commerce (WooCommerce + payment gateway) 8-13 points 24-80 hours (3-5 days to 1-2 weeks) Full store setup, payment processing, shipping, taxes

Plugin Budget: Recommend < 15 plugins total for performance (< 20 maximum with strong justifications).

Hour Calculation for CSV Export

When the csv-exporter skill generates the Teamwork backlog CSV, the "Estimated time" column is populated using these conversions:

Format Guidelines: - 1-2 points: Use exact hours (e.g., "2h", "4h") - 3-5 points: Use hour ranges or days (e.g., "6-8h", "1 day", "12-16h", "2 days") - 8+ points: Use day ranges or weeks (e.g., "3-4 days", "1-2 weeks")

Examples:

Tasklist,Task,Tags,Estimated time
"Phase 1","[EPIC] Theme Foundation [8 points]","SP-8,Phase-1","24-32h"
"Phase 1","- [TASK] theme.json configuration [3 points]","SP-3,Phase-1","1 day"
"Phase 1","- [TASK] Basic templates [2 points]","SP-2,Phase-1","4h"
"Phase 2","[EPIC] Block Patterns [13 points]","SP-13,Phase-2","1-2 weeks"
"Phase 2","- [PATTERN] Hero section [2 points]","SP-2,Phase-2","4h"
"Phase 2","- [PATTERN] Feature grid [2 points]","SP-2,Phase-2","4h"
"Phase 3","[CUSTOM] Pricing calculator [13 points]","SP-13,Phase-3","1-2 weeks"

Decision Framework Impact on Estimates

The Pattern-First Framework: 1. Try Core Blocks First → 1-3 points (2-8 hours) 2. Compose Patterns Second → 2-5 points (4-20 hours) 3. Use ACF Blocks Third → 2-5 points (4-20 hours) + ACF PRO cost 4. Build Custom Blocks Last → 3-21 points (12-120 hours)

Cost Multipliers: - Pattern → ACF Block: 2-3x longer - Pattern → Custom Block: 3-10x longer - ACF Block → Custom Block: 2-5x longer

Example: Team Member Directory

Approach Story Points Time Cost at $100/hr
Pattern (repeating Group blocks) 2 points 4 hours $400
ACF Block 3 points 6-8 hours $600-800
Custom Gutenberg Block 8 points 24-32 hours $2,400-3,200

Key Insight: For most UI components (80-90%), patterns or ACF blocks are sufficient. Custom blocks should be < 10-20% of total development.

WordPress Estimation Checklist

Before providing estimates, verify:

  • Decision framework applied - Core → Pattern → ACF → Custom (in order)
  • Justification documented - Why this approach vs alternatives?
  • Performance budget included - Core Web Vitals optimization (5-8 points)
  • Plugin budget considered - < 15 plugins target, justifications documented
  • ACF PRO cost noted - If using ACF blocks, note $49-249/year license
  • Testing included - Browser testing (2 points), accessibility (3 points), performance (2 points)
  • Documentation included - Pattern library, editor training, developer README

Velocity Calculation

Team velocity is the average story points completed per sprint.

Formula

Velocity = (Team Size × Hours/Sprint × Productive %) / Hours per Point

Example Calculation

Team: - 3 developers - 2-week sprints (80 hours/developer) - 70% productive time (30% for meetings, admin, etc.) - 6 hours per story point (team average)

Calculation:

3 developers × 80 hours × 0.70 / 6 hours per point = 28 points per sprint

Calibrating Velocity

After a few sprints, use historical data:

  1. Track completed points per sprint
  2. Calculate average over 3-5 sprints
  3. Adjust estimates if consistently over/under
  4. Re-calibrate when team changes

Breaking Down Large Items

13 Points: Should Break Down

13-point items should typically be broken into smaller stories:

Example: User Management System [13 points]

Break into: - User Registration Flow [5 points] - User Login Flow [3 points] - Password Reset [2 points] - Profile Management [3 points]

Total: 13 points (same estimate, but broken down)

21 Points: Must Break Down

21-point items are too large for a single sprint and must be decomposed:

Example: Complete Theme Development [21 points]

Break into: - Base Theme Setup [5 points] - Component Library [8 points] - Page Templates [5 points] - Responsive Styles [3 points]

Total: 21 points (spread across multiple sprints)

34+ Points: Decompose First

Items over 34 points should be broken into multiple epics:

Example: E-commerce Platform [89 points]

Break into epics: - Product Management [21 points] - Shopping Cart [13 points] - Checkout Flow [21 points] - Payment Processing [13 points] - Order Management [21 points]

Total: 89 points (5 epics)

Estimation Workshop

Planning Poker

  1. Present user story - Product owner explains requirement
  2. Ask questions - Team clarifies understanding
  3. Individual estimates - Each person picks a card (1, 2, 3, 5, 8, 13, 21)
  4. Reveal simultaneously - Everyone shows their card
  5. Discuss differences - Highest and lowest explain reasoning
  6. Re-estimate - Repeat until consensus

Relative Estimation

Compare to known tasks:

  • "This is about the same as the login form we built" → 5 points
  • "This is more complex than search but simpler than checkout" → between 8 and 13
  • "This is twice as complex as the user profile" → double the points

T-Shirt Sizing (Initial Estimates)

For rough initial estimates, use T-shirt sizes:

  • XS → 1-2 points
  • S → 3-5 points
  • M → 8 points
  • L → 13 points
  • XL → 21 points
  • XXL → Must decompose

Convert to Fibonacci numbers for sprint planning.

Common Estimation Mistakes

❌ Too Precise

Wrong: "This is 4.5 story points" Right: "This is between 3 and 5, let's call it 5"

Story points are relative, not precise time measurements.

❌ Time-Based Thinking

Wrong: "8 hours = 1 day = 8 points" Right: "This is more complex than a 5-pointer but less than a 13"

Think complexity, not time.

❌ Individual Capacity

Wrong: "I can do 40 points this sprint" Right: "Our team velocity is 28 points per sprint"

Story points are team-based, not individual.

❌ Ignoring Uncertainty

Wrong: "We've done this before, it's still 5 points even with new tech" Right: "New tech adds uncertainty, this is 8 points"

Higher uncertainty = higher points.

❌ Not Including Everything

Wrong: "5 points for coding" (forgetting testing, review, documentation) Right: "5 points for full implementation including tests and review"

Include all work in the estimate.

Re-estimation

When to Re-estimate

  • Requirements change significantly
  • Technical approach changes
  • New information discovered
  • Team composition changes
  • Velocity consistently off

How to Re-estimate

  1. Review original estimate and reasoning
  2. Identify what changed - new requirements? tech change?
  3. Estimate new work separately if possible
  4. Adjust total - add points for new complexity
  5. Document change - note why re-estimated

Example

Original: API Integration [5 points] - Simple REST API - JSON response - Standard authentication

Re-estimated: API Integration [13 points] - Discovered: SOAP API (not REST) - XML parsing required - OAuth 2.0 with refresh tokens - Rate limiting to handle

Reasoning: Complexity increased significantly with legacy SOAP API and OAuth requirements.

Story Points in FRDs

CMS Planner includes story points throughout the FRD:

In Requirements Section

## FR-001: saplings_person Recipe [MUST HAVE]

**Story Points:** 34 points

- Recipe creation and config export: 13 points
- Field definitions (including shared storage): 8 points
- Views and Pathauto configuration: 5 points
- Testing and documentation: 5 points
- Demo content creation: 3 points

In Implementation Plan

## Phase 2: Core Recipes [168 points]

### Epic 1: saplings_person Recipe [34 points]
- Story 1: Content type and fields [13 points]
- Story 2: Taxonomies and views [8 points]
- Story 3: Pathauto and metatag [5 points]
- Story 4: Demo content [3 points]
- Story 5: Testing and documentation [5 points]

In CSV Backlog

Tasklist,Task,Tags
"Phase 2","[EPIC] saplings_person [34 points]","SP-34,Phase-2"
"Phase 2","- [STORY] Content type [13 points]","SP-13,Phase-2"
"Phase 2","-- [TASK] Field definitions [5 points]","SP-5,Phase-2"